Rob is responsible for estimating a work package that has a significant amount of uncertainty associated with the time and cost to complete. Due to the uncertainty involved he will be making a low, an average and a high estimate. Rob is using which estimating approach?

+2
Answers (1)
  1. 17 December, 12:43
    0
    Range estimating.

    Explanation:

    Range estimation is an estimation approach that allows an interested person to have much relevant information about the nature of a task being set. Through this estimate it is possible to have more confidence or more uncertainty in a project that is being stipulated and that may result in a large profit or a great loss.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Rob is responsible for estimating a work package that has a significant amount of uncertainty associated with the time and cost to ...” in 📗 Social Studies if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers