In slab placement, what comes directly before concrete floating? Select one: a. Formwork placement b. Curing c. Troweling d. Pouring e. Strike-off

+3
Answers (1)
  1. 18 May, 10:04
    0
    e. Strike-off

    Explanation:

    The precast suspended slabs are considered by pouring the slabs in a framework of the slabs and then lifting the slabs into suspended postilions in the structure.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “In slab placement, what comes directly before concrete floating? Select one: a. Formwork placement b. Curing c. Troweling d. Pouring e. ...” in 📗 Social Studies if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.