Earl is preparing a risk register for his organization's risk management program. Which data element is LEAST likely to be included in a risk register?

+5
Answers (1)
  1. 30 May, 20:06
    0
    Answer: Risk survey results

    Explanation: Risk register contains the outcomes of the other risk management processes as they are conducted, resulting in an increase in the level and type of information contained in the risk register over time.

    Components of a risk register are list of identified risks, list of potential responses, secondary risks and residual risks. These are most likely included in a risk register.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Earl is preparing a risk register for his organization's risk management program. Which data element is LEAST likely to be included in a ...” in 📗 Social Studies if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.