Which of the following responses identifies a common type of logical dependency used to sequence project activities?

a. last-in; last-out

b. finish-to-start

c. first-in; first-out

d. last-in; first-out

+1
Answers (1)
  1. 12 May, 10:42
    0
    b. finish-to-start

    Explanation:

    Activity dependencies or activity relationships are of four types.

    Finish-to-Start: Activity B cannot start until the activity A finishes. Start-to-Start: The activity B cannot start until the activity A starts. Start-to-Finish: The activity B cannot finish until the activity A starts. Finish-to-Finish: The activity B cannot finish until the activity A finishes.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Which of the following responses identifies a common type of logical dependency used to sequence project activities? a. last-in; last-out ...” in 📗 Social Studies if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers