Ask Question
15 January, 08:07

If an organization or subcontractor has performed similar projects in the past and has kept records of how long specific activities actually took, these historical data

can be used as a guide in estimating the durations of similar activities for future projects. (T/F)

+5
Answers (1)
  1. 15 January, 08:35
    0
    Answer: True

    Explanation:

    The previous or similar projects would be a better reference when considering a new project and the new project would be at advantage because mistakes and errors made from previous project would be avoided in the new project.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “If an organization or subcontractor has performed similar projects in the past and has kept records of how long specific activities ...” in 📗 Social Studies if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers