John at Tim's Toys was working on a custom-made miniature car for a customer. The job, BCB101, was begun in March. At the end of March, the job cost sheet for BCB101 showed direct materials of $6,000, direct labor of 200 hours at $75 per hour, and overhead of 50% of direct labor cost. During April, John's time ticket showed 50 hours on Job BCB101, 25 hours on Job BCB102, and 40 hours on a new job, BCB103. What is the total amount of overhead applied to Job BCB101?

+5
Answers (1)
  1. 7 May, 17:45
    0
    Applied overhead = $9,375

    Explanation:

    Giving the following information:

    The job, BCB101, was begun in March. At the end of March, the job cost sheet for BCB101 showed direct materials of $6,000, direct labor of 200 hours at $75 per hour, and overhead of 50% of direct labor cost.

    During April, John's time ticket showed 50 hours on Job BCB101.

    Applied overhead = (200*75) * 0.5 + (50*75) * 0.5 = $9,375
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “John at Tim's Toys was working on a custom-made miniature car for a customer. The job, BCB101, was begun in March. At the end of March, the ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers