Ask Question
3 November, 16:47

Your company is considering submitting a bid on a major project. You determine that the expected completion time is 100 weeks and the standard deviation is 10 weeks. It is assumed that the normal distribution applies. You wish to set the due date for the project such that there is an 85 percent chance that the project will be finished by this time. What due date should be set

+4
Answers (1)
  1. 3 November, 16:55
    0
    Due date to be set is 110 weeks

    Explanation:

    Expected completion time = 100 weeks

    Standard deviation, s = 10 weeks

    P (x
    P (Z< (k-u) / s) = 0.85

    from the standard normal distribution table 0.85 = P (Z<1.037)

    (k-u) / s = 1.307

    k = 110.37 weeks
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Your company is considering submitting a bid on a major project. You determine that the expected completion time is 100 weeks and the ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers