Johnson Construction Company uses cost-plus pricing to determine costs and place bids on local jobs. The manager needs to compute the cost-plus price to place a bid on a community swimming pool, deck, and spa. The estimated cost associated with the new project is $225,000. The markup on the project cost is 40%. What is the cost-plus price required to bid on the new project?

+2
Answers (1)
  1. 2 June, 00:01
    0
    Price = $315,000

    Explanation:

    Giving the following information:

    The manager needs to compute the cost-plus price to place a bid on a community swimming pool, deck, and spa. The estimated cost associated with the new project is $225,000. The markup on the project cost is 40%.

    Price = 225,000 * 1.40 = $315,000
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Johnson Construction Company uses cost-plus pricing to determine costs and place bids on local jobs. The manager needs to compute the ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers