Scrum uses a series of coordinated meetings to manage the development process. Which of the following is held at the start of each sprint? During this meeting the product owner and development team negotiate which product backlog items the team will attempt during the next sprint.

+2
Answers (1)
  1. 24 July, 00:53
    0
    Sprint planning meeting

    Explanation:

    Sprint planning is a joint effort involving a person on the team who is responsible for managing the process and organizing the meeting.

    It also involves a Product Owner clarifying the specifics of the product backlog items and their respective acceptance requirements, and the Entire Agile Team identifying the work and effort needed to fulfill their sprint engagement.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Scrum uses a series of coordinated meetings to manage the development process. Which of the following is held at the start of each sprint? ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers