Cala Manufacturing purchases land for $390,000 as part of its plans to build a new plant. The company pays $33,500 to tear down an old building on the lot the and $47,000 to fill and level the lot. It also pays construction costs of $1,452,200 for the new building and $87,800 for lighting and paving a parking area. Prepare a single journal entry to record these costs incurred by Cala, all of which are paid in cash.

+1
Answers (1)
  1. 23 July, 22:50
    0
    The journal entry is shown below:

    Land A/c Dr $470,500

    Land Improvement A/c Dr $87,800

    Building A/c Dr $1,452,200

    To Cash A/c $2,010,500

    (Being these costs are recorded)

    The computation of the land is shown below:

    = Purchase cost of new plant + tear down cost + fill and level the lot cost

    = $390,000 + $33,500 + $47,000

    = $470,500
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Cala Manufacturing purchases land for $390,000 as part of its plans to build a new plant. The company pays $33,500 to tear down an old ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.