Ask Question
2 September, 09:50

Maysonet Corporation uses a job-order costing system and has provided the following partially completed T-account summary for the past year. Work in ProcessBal. 1/1 18,000 CreditsDebits 520,000 Bal. 12/31 34,000

The cost of completed jobs transferred from Work in Process to Finished Goods during the year was : a) $504,000b) $572,000c) $520,000d) $538,000

+4
Answers (1)
  1. 2 September, 10:08
    0
    The cost of completed jobs transferred from Work in Process to Finished Goods during the year was a) $504,000

    Explanation:

    The cost of completed jobs transferred from Work in Process to Finished Goods during the year = Credits Work in Process = Work in Process Bal. 1/1 + Debits Work in Process - Work in ProcessBal. 12/31

    Maysonet Corporation provided they completed T-account summary for the past year: Work in Process Bal. 1/1 $18,000 Debits $520,000 Bal. 12/31 $34,000

    The cost of completed jobs transferred from Work in Process to Finished Goods during the year = $18,000 + $520,000 - $34,000 = $504,000
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Maysonet Corporation uses a job-order costing system and has provided the following partially completed T-account summary for the past ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers