In a normal costing system, the cost of a job includes
A. actual direct materials, actual direct labor, and estimated (applied) overhead.
B. estimated direct materials, estimated direct labor, and estimated overhead.
C. actual direct materials, actual direct labor, actual overhead, and actual selling cost.
D. actual direct materials, actual direct labor, and actual overhead.
E. None of these. Job-order costing requires the use of actual, not normal, costing.
+1
Answers (1)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “In a normal costing system, the cost of a job includes A. actual direct materials, actual direct labor, and estimated (applied) overhead. ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Home » Business » In a normal costing system, the cost of a job includes A. actual direct materials, actual direct labor, and estimated (applied) overhead. B. estimated direct materials, estimated direct labor, and estimated overhead. C.