Asper Corporation has provided the following data for February. Denominator level of activity 7,700 machine-hours Budgeted fixed manufacturing overhead costs $ 266,420 Fixed component of the predetermined overhead rate $ 34.60 per machine-hour Actual level of activity 7,900 machine-hours Standard machine-hours allowed for the actual output 8,200 machine-hours Actual fixed manufacturing overhead costs $ 259,960 The budget variance for February is:

+2
Answers (1)
  1. 18 August, 14:28
    0
    Asper Corporation has provided the following data for February. Denominator level of activity 7,700 machine-hours Budgeted fixed manufacturing overhead costs $ 266,420 Fixed component of the predetermined overhead rate $ 34.60 per machine-hour Actual level of activity 7,900 machine-hours Standard machine-hours allowed for the actual output 8,200 machine-hours Actual fixed manufacturing overhead costs $ 259,960 The budget variance for February is $6,460 Favorable.

    Explanation:

    Budgeted fixed manufacturing overhead cost = $266,420.

    Actual fixed manufacturing overhead costs = $259,960

    The budget variance for February is calculated as below:

    Budget Variance = Actual Fixed Manufacturing Overheads - Budgeted Fixed Manufacturing Overheads

    Budget Variance = $259,960 - $ 266,420.

    Budget Variance = - $6,460

    Budget Variance = $6,460 Favorable