New Company has the following information available for variable overhead costs. Direct labor hours are the cost driver for variable overhead costs. Actual variable overhead costs $3,500 Standard variable overhead costs $1.50 per hour Actual direct labor hours 2,500 hours Standard direct labor hours per unit 5 hours Units produced 500 What is the variable overhead spending variance?

+4
Answers (1)
  1. 10 October, 22:01
    0
    Variable overhead spending variance is $250 favorable.

    Explanation:

    Variable overhead spending variance

    SR = Standrad variable overhead cost = $1.50

    AR = Actual variable overhead cost = $3,500

    AH = Actual Hours work = 2,500 hours

    = (SR*AH) - AR

    = (1.50*2,500) - 3,500

    =3,750 - 3,500

    =$250 favorable
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “New Company has the following information available for variable overhead costs. Direct labor hours are the cost driver for variable ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.