Ask Question
5 August, 10:57

A service contract for a video projection system costs $80 a year. You expect to use the system for four years. Instead of buying the service contract, what would be the future value of these annual amounts after four years if you earn 2 percent on your savings

+3
Answers (1)
  1. 5 August, 11:19
    0
    The future value at the end of year 4 will be $329.73

    Explanation:

    This can be found using the following annuity formula:

    Future Value = Present Value * Annuity Factor (@2% for 4 Years)

    Future Value = $80 * 4.121 = $329.73
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “A service contract for a video projection system costs $80 a year. You expect to use the system for four years. Instead of buying the ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers