Ask Question
7 June, 09:37

Use the following information:

Food Goblin Supermarkets use both cashiers and baggers to serve customers at check out. During the first 6 hours of each workday (Monday-Friday), 4 cashiers and 2 baggers serve approximately 40 customers per hour. A cashier requires approximately 5 minutes at checkout while a bagger requires approximately 2 minutes at bagging to serve each customer.

What is the weekly capacity of the cashier operation? Select one:

a) 60 hours/week

b) 120 hours/week

c) 180 hours/week

d) 30 hours/week

e) None of the above

+4
Answers (1)
  1. 7 June, 09:48
    0
    e. None of the above

    300 customers per week

    Explanation:

    The computation of weekly capacity of the cashier operation is shown below:-

    4 Cashiers managed to deliver 40 customers an hour production to the beggars.

    So, for 1 cashier the capacity will be 10 customers per hour.

    Now, in a week of 5 days and 6 hours per day,

    we have a total of 30 hours

    The one single cashier the capacity will be

    Capacity = Total hours * Customer per hour

    30 * 10

    = 300 customers per week

    Therefore option is not available
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Use the following information: Food Goblin Supermarkets use both cashiers and baggers to serve customers at check out. During the first 6 ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers