Management recently instituted a new training program for upper level managers. they budgeted the cost of the new program at $1,000 per employee trained but actual costs were $1,250 per employee trained. the difference between the budgeted cost for training and the actual cost of training is called a:

+3
Answers (1)
  1. 26 October, 15:02
    0
    The difference between the actual and budgeted cost is termed the variance. In this case, that variance shows that the training program ran over budget by $250 per employee.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Management recently instituted a new training program for upper level managers. they budgeted the cost of the new program at $1,000 per ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.