An end item "A" is assembled from two "B" components and two "C" subassemblies. The "C" subassembly is composed of one of each component "B" and "D." If the gross requirement for "A" is 100 units, what is the demand for component "B"?

+3
Answers (1)
  1. 12 March, 10:52
    0
    400 units
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “An end item "A" is assembled from two "B" components and two "C" subassemblies. The "C" subassembly is composed of one of each component ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.