Assume that overhead is charged on a flat-rate basis. Each member of the project is assigned an overhead charge of $100/week. What would the fully loaded cost of labor be for an employee, given that she is assigned to the project for 280 hours at $15/hour? Hint: The hours that the employee works (280 hours) would equate to 7 weeks.

+5
Answers (1)
  1. 15 June, 23:45
    0
    Total cost = $4,900

    Explanation:

    Giving the following information:

    Each member of the project is assigned an overhead charge of $100/week. What would the fully loaded cost of labor be for an employee, given that she is assigned to the project for 280 hours at $15/hour? Hint: The hours that the employee works (280 hours) would equate to 7 weeks.

    Total cost = direct labor + allocated overhead

    Total cost = 280*15 + 100*7 = $4,900
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Assume that overhead is charged on a flat-rate basis. Each member of the project is assigned an overhead charge of $100/week. What would ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers