A goal programming problem had two goals (with no priorities assigned). Goal number 1 was to achieve a profit of $2,400 and goal number 2 was to have no idle time for workers in the factory. The optimal solution to this problem resulted in a profit of $2,300 and no idle time. What was the value for the objective function for this goal programming problem?

+2
Answers (1)
  1. 6 August, 07:39
    0
    100

    Explanation:

    Goal programming is an optimization technique that allows for multiple, normally conflicting objectives and then attempts to solve each goal sequentially to a satisfactory level. In goal programming, differential variables are being used.

    Since the goal programming problem had two goals. Goal number 1 was to achieve a profit of $2,400 and goal number 2 was to have no idle time for workers in the factory. The optimal solution to this problem resulted in a profit of $2,300 and no idle time

    This means that goal number 2 was achieved since the optimal solution resulted in no idle time. But goal number 1 was not achieved because a profit of $2300 was achieved in the solution instead of $2400.

    Therefore, the value for the objective function for this goal programming problem = 2400 - 2300 = 100
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “A goal programming problem had two goals (with no priorities assigned). Goal number 1 was to achieve a profit of $2,400 and goal number 2 ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.