Summerlin Company budgeted 4,200 pounds of material costing $4.00 per pound to produce 2,300 units. The company actually used 4,700 pounds that cost $4.10 per pound to produce 2,300 units. What is the direct materials quantity variance?

A. $420 unfavorable.

B. $470 unfavorable.

C. $2,000 unfavorable.

D. $2,470 unfavorable.

E. $2,050 unfavorable.

+5
Answers (1)
  1. Today, 03:21
    0
    Option (C) is correct.

    Explanation:

    Given that,

    Standard Quantity = 4,200

    Actual Quantity = 4,700

    Standard Price = $4

    Cost = $4.10 per pound to produce 2,300 units

    Direct Material Quantity variance:

    = (Standard Quantity - Actual Quantity) * Standard Price

    = (4,200 - 4,700) * $4

    = $2,000 Unfavorable

    Therefore, the direct materials quantity variance is $2,000 Unfavorable.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Summerlin Company budgeted 4,200 pounds of material costing $4.00 per pound to produce 2,300 units. The company actually used 4,700 pounds ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.