Delta Construction Corporation, a general contractor, hires Eagle Electrical Company, a subcontractor, to wire a new office building. As the work progresses, Delta pays Eagle some of the price, but after completing most of the job, Eagle is owed more than $50,000. Eagle stops work to insist on being paid. Delta hires Fine Wiring, Inc., to finish the job. Eagle files a suit against Delta. Eagle's suspension of work is most likely

+3
Answers (1)
  1. 20 June, 11:37
    0
    Answer: excused by Delta's failure to pay.

    Explanation:

    Delta Construction Corporation hires Eagle Electrical Company, as a subcontractor, to wire its new office building. After the completion of the work, Eagles is owed more than $50000.

    Eagle's suspension of work is most likely due to the excuse by Delta's failure to pay. Delta has a right to pay up the money owed to Eagle. Lack of payment can lead to court cases.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Delta Construction Corporation, a general contractor, hires Eagle Electrical Company, a subcontractor, to wire a new office building. As ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers