Part X requires machining on a milling machine (operations A and B are required).
Find the number of machines required to produce 3000 parts per week. Assume the company will be operating five days per week, 18 hours per day. The following infor - mation is known:
Operation Standard Time Efficiency Reliability Scrap
A 3 min 95% 95% 2%
B 5 min 95% 90% 5%
Note: The milling machine requires tool changes and preventive maintenance after every lot of 500 parts. These changes require 30 minutes.
+5
Answers (1)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Part X requires machining on a milling machine (operations A and B are required). Find the number of machines required to produce 3000 ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Home » Business » Part X requires machining on a milling machine (operations A and B are required). Find the number of machines required to produce 3000 parts per week. Assume the company will be operating five days per week, 18 hours per day.