Scoresby Co. uses 6 machine hours and 2 direct labor hours to produce Product X. It uses 8 machine hours and 16 direct labor hours to produce Product Y. Scoresby's Assembly and Finishing departments have factory overhead rates of $240 per machine hour and $160 per direct labor hour, respectively. How much total factory overhead will be allocated to a unit of each of the two products

+4
Answers (1)
  1. 8 August, 10:53
    0
    For product X = $1,760

    And for product Y = $4,480

    Explanation:

    The computation of total factory overhead cost for two products are as follows

    For product X and Product Y

    = Number of machine hours * factory overhead rate per machine hour + Number of direct labor hours * factory overhead rate per direct labor hour

    = 6 * $240 + 2 * $160 + 8 * $240 + 16 * $160

    = $1,440 + $320 + $1,920 + $2,560

    = $1,760 + $4,480

    = $6,240

    So for product X = $1,760

    And for product Y = $4,480
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Scoresby Co. uses 6 machine hours and 2 direct labor hours to produce Product X. It uses 8 machine hours and 16 direct labor hours to ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.