Fleck's standard quantities for 1 unit of product include 2 pounds of materials and 1.5 labor hours. The standard rates are $4 per pound and $14 per hour for direct labor. The standard overhead rate is $16 per direct labor hour.

The total standard cost of Fleck's product is how much?

a. $34

b. $29

c. $45

d. $53

+3
Answers (1)
  1. 27 July, 09:28
    0
    d. $53

    Explanation:

    The computation of the total standard cost is shown below

    = Standard rate per pound * number of pounds + standard rate per direct labor hour * number of direct labor hour + standard overhead rate * number of direct labor hour

    = $4 per pound * 2 pounds + $14 per direct labor hour * 1.5 labor hour + $16 per direct labor hour * 1.5 labor hour

    = $8 + $21 + $24

    = $53
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Fleck's standard quantities for 1 unit of product include 2 pounds of materials and 1.5 labor hours. The standard rates are $4 per pound ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.