Koki, a production manager, was engaged in the development of a core component of a machine. He realized that the component would not be ready for QC testing as per the fixed deadline and suggested allotting two more weeks for its complete development or sending only a part of it for testing in the first cycle. Which two decision-making steps does this represent?

a) recognize the need for a decision and choose among alternatives

b) choose among alternatives and assess alternatives

c) recognize the need for a decision and generate alternatives

d) generate alternatives and choose among alternatives

+2
Answers (1)
  1. 10 January, 14:28
    0
    recognize the need for a decision and generate alternatives
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Koki, a production manager, was engaged in the development of a core component of a machine. He realized that the component would not be ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers