A production line is to be designed for a job with three tasks. The task times are 0.3 minutes, 1.4 minutes, and 0.7 minutes. The minimum cycle time in minutes is:

+2
Answers (1)
  1. 16 March, 22:34
    0
    Answer: 1.4 minutes

    Explanation:

    Given that,

    Task time (1) = 0.3 minutes

    Task time (2) = 1.4 minutes

    Task time (3) = 0.7 minutes

    Minimum cycle time refers to the task which has the longest task time.

    Maximum cycle time is simply the sum of all the task time.

    Therefore,

    Minimum cycle time = Length of longest task time

    = Task time (2)

    = 1.4 minutes
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “A production line is to be designed for a job with three tasks. The task times are 0.3 minutes, 1.4 minutes, and 0.7 minutes. The minimum ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.