Livermore Industries uses a kanban system to manage production of the KR-9 subassembly. In a ten-hour day, they use 1500 units and use containers that can hold 50 units each. It takes 45 minutes to fill and move a container of parts to the right place on the KR-9 line that is currently rated at a 15% safety factor. How many production cards are needed

+2
Answers (1)
  1. 21 November, 00:03
    0
    3 cards are required since given problem statement states that 15% as safety factor.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Livermore Industries uses a kanban system to manage production of the KR-9 subassembly. In a ten-hour day, they use 1500 units and use ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.