A manufacturer planned to use $97 of materials per unit produced, but in the most recent period it actually used $95 of material per unit produced. During this same period, the company planned to produce 2,850 units, but actually produced only 2,500 units. The flexible-budget variance for materials, to the nearest dollar, is:

+5
Answers (1)
  1. 17 December, 11:56
    0
    The flexible-budget variance for materials is $5,000 favorable.

    Explanation:

    In order to calculate the The flexible-budget variance for materials we have to use the following formula:

    Flexible budget variance for materials = Budgeted material cost for actual production - Actual material cost

    = (2,500*$97) - (2,500*$95)

    = $242,500-$237,500

    = $5,000

    Hence, The flexible-budget variance for materials is $5,000 favorable.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “A manufacturer planned to use $97 of materials per unit produced, but in the most recent period it actually used $95 of material per unit ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.