Ask Question
9 May, 08:36

Takt time is calculated as Demand volume divided by customer required volume Customer required volume divided by available work time Available work time divided by customer required volume Available work time divided by demand volume

+3
Answers (1)
  1. 9 May, 08:45
    0
    The correct answer is letter "C": Available work time divided by customer required volume.

    Explanation:

    Takt time refers to the time producers have to create a good or service to satisfy consumers' demands. It is calculated by dividing the net available time for the production of the goods or services by the customers' demand on a daily basis. Takt time is a measure based on the manufacturer's production process practices.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Takt time is calculated as Demand volume divided by customer required volume Customer required volume divided by available work time ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers