Vita Live has authorized the development of a video game based on a new

technology. Which of the following is an example of a risk that has to be

accepted because it cannot be mitigated?

O

A. There is a risk that the lead developer may work too slowly.

O

B. There is a risk that a competitor may beat them to market with a

similar product

O

C. There is a risk that the development costs will exceed the budget.

O

D. There is a risk that program engineers will leave and start their

own company based on the same work.

+5
Answers (1)
  1. 31 March, 17:47
    0
    B. There is a risk that a competitor may beat them to market with a

    similar product

    Explanation:

    apex
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Vita Live has authorized the development of a video game based on a new technology. Which of the following is an example of a risk that has ...” in 📗 Computers & Technology if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.