With respect to PERT and CPM, slack A. is a task or subproject that must be completed. B. marks the start or completion of a task. C. is the amount of time a task may be delayed without changing the overall project completion time. D. is the latest time an activity can be started without delaying the entire project.
+4
Answers (1)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “With respect to PERT and CPM, slack A. is a task or subproject that must be completed. B. marks the start or completion of a task. C. is ...” in 📗 Computers & Technology if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.