Ask Question

Which is the least appropriate join operation forPipeline parallelism? Hash joinInner JoinOuter JoinSort-merge joinNone of the above.

+4
Answers (1)
  1. 9 December, 01:09
    0
    Answer: Hash join

    Explanation: Pipeline parallelism is a way in which multiple path depend on one another. But there is a possibility of overlapping of execution and the output of one step is released as input to consecutive step. Hash join is used for the joining of the algorithm applied on equal joins and is separated in form of columns and so does not follow the overlap in the execution and is much slower join for the pipeline parallelism.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Which is the least appropriate join operation forPipeline parallelism? Hash joinInner JoinOuter JoinSort-merge joinNone of the above. ...” in 📗 Computers & Technology if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers