A canoe requires 8 hours of fabrication and a rowboat 5 hours. The fabrication departments has at most 107 hours of labor available each week. Let X be the number of canoes and let Y be the number of rowboats. Select the correct letter for answerA) 8x+5y<107B) 5x+8y107D) 5x+8y>107

+3
Answers (1)
  1. 6 September, 13:29
    0
    Answer: A

    Step-by-step explanation: Canoe → 8h →X

    Rowboat → 5h → Y

    Fabrication department has at most 107, which means it need to be less than 107 hours.

    This way, the amount of time to fabricate X canoes = 8X plus the amount of time to fabricate Y Rowboat = 5Y must be less than 107.

    8X + 5Y < 107
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “A canoe requires 8 hours of fabrication and a rowboat 5 hours. The fabrication departments has at most 107 hours of labor available each ...” in 📗 Mathematics if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.