The total cost for a job is 1,766. the cost for material is 847.00. 3 employees are paid 8 dollars an hour for 22 hours of work. what is your profit

+3
Answers (1)
  1. 14 February, 11:17
    0
    Total cost = 1766

    Material cost=847

    3 employees are paid 8 dollars an hour for 22 hours so

    Labor cost=8*22=176

    Profit=total cost - (material cost+labor cost)

    Profit=1,766 - (847+176) = 743
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “The total cost for a job is 1,766. the cost for material is 847.00. 3 employees are paid 8 dollars an hour for 22 hours of work. what is ...” in 📗 Mathematics if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.