A factory has 115 ceiling fans in stock. If the factory can manufacture 12 fans each hour, how long would it take the factory to complete an order for 500 ceiling fans? Round your answer to the nearest tenth of an hour.

+3
Answers (1)
  1. 9 September, 12:53
    0
    Y = 12x + 115 ... where x is the number of hrs and y is the number of fans

    an order for 500 fans ...

    500 = 12x + 115

    500 - 115 = 12x

    385 = 12x

    385/12 = x

    32.08 rounds to 32.1 < = = = it would take 32.1 hrs
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “A factory has 115 ceiling fans in stock. If the factory can manufacture 12 fans each hour, how long would it take the factory to complete ...” in 📗 Mathematics if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.