X and Y together complete a task in 4 days, Y and Z together in 5 days. If they work independently, who will finish the work in the least time? A. X B. Y C. Z D. Not enough information to decide

+2
Answers (1)
  1. 15 December, 03:53
    0
    c, Z

    Step-by-step explanation:

    x+y=4

    y+z=5

    y=4-x

    4-x+z=5

    -x+z=1

    z=1+x
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “X and Y together complete a task in 4 days, Y and Z together in 5 days. If they work independently, who will finish the work in the least ...” in 📗 Mathematics if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.