Rice Corporation uses the cost formula Y=$4800 + $0.40X for the maintenance cost, where X is machine hours. The August budget is based on 9,000 hours of planned machine time. What is the maintenance cost expected to be incurred during August? (A) $4,800; (B) $8,400; (C) $3,600: (D) $1,200

+4
Answers (1)
  1. 16 December, 16:49
    0
    correct answer is option B

    Step-by-step explanation:

    rice corporation cost formula for maintenance:

    Y = $4800 + $0.40 X

    where, X is machine hours

    So,

    in august budget hours given is = 9000.

    Now, substituting the value of hours in the given formula,

    we get,

    Y = $4800 + $0.40 * (9000)

    Y = $4800 + $3600

    Y = $8400

    hence, the maintenance incurred during August month is $8400

    So, the correct answer is option B
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Rice Corporation uses the cost formula Y=$4800 + $0.40X for the maintenance cost, where X is machine hours. The August budget is based on ...” in 📗 Mathematics if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.