At a construction site, the site manager notices that a crane takes 20 seconds to lift a 500kg steel beam up to a height of 15 meters. From this information, he calculates the power output of the crane to be what value?

+4
Answers (1)
  1. 11 July, 14:58
    0
    The work done is equal to the change in potential energy which is:

    P. E = mgh

    P. E = 500 x 9.81 x 15

    P. E = 73,575 J

    Power = work / time

    Power = 73,575 / 20

    Power = 3,700 Watts
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “At a construction site, the site manager notices that a crane takes 20 seconds to lift a 500kg steel beam up to a height of 15 meters. From ...” in 📗 Physics if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.