Ask Question
29 April, 13:04

Cables and conductors installed on the side of a pole or building shall be protected up to ___feet above finished grade.

+2
Answers (1)
  1. 29 April, 13:30
    0
    10 feet.

    Explanation:

    Conductors are considered outside the building when they installed. The requirement of NEC is above 10 feet for the clearance after the final grade for service conductors and cables where they are connected with the building, above the sidewalks and the to other areas which are accessible to the pedestrians.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Cables and conductors installed on the side of a pole or building shall be protected up to ___feet above finished grade. ...” in 📗 Physics if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers