Ask Question
22 February, 15:24

Markowis Corp. has collected the following data concerning its maintenance costs for the past 6 months.

Units Produced Total Cost

July 18,000 $36,000

August 32,000 48,000

September 36,000 55,000

October 22,000 38,000

November 40,000 74,500

December 38,000 62,000

Required:

Compute the variable and fixed cost elements using the high low method.

+5
Answers (1)
  1. 22 February, 15:45
    0
    Variable cost per unit = $1.75

    Fixed costs = $4,500

    Explanation:

    Giving the following information:

    Units Produced Total Cost

    July 18,000 $36,000

    August 32,000 48,000

    September 36,000 55,000

    October 22,000 38,000

    November 40,000 74,500

    December 38,000 62,000

    To calculate the variable and fixed costs under the high-low method, we need to use the following formulas:

    Variable cost per unit = (Highest activity cost - Lowest activity cost) / (Highest activity units - Lowest activity units)

    Variable cost per unit = (74,500 - 36,000) / (40,000 - 18,000)

    Variable cost per unit = $1.75

    Fixed costs = Highest activity cost - (Variable cost per unit * HAU)

    Fixed costs = 74,500 - (1.75*40,000)

    Fixed costs = $4,500

    Fixed costs = LAC - (Variable cost per unit * LAU)

    Fixed costs = 36,000 - (1.75*18,000)

    Fixed costs = $4,500
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Markowis Corp. has collected the following data concerning its maintenance costs for the past 6 months. Units Produced Total Cost July ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers