Tungsten, Inc. manufactures both normal and premium tube lights. The company allocates manufacturing overhead using a single plantwide rate with machine hours as the allocation base. Estimated overhead costs for the year are $ 104 comma 000. Additional estimated information is given below. Normal Premium Machine hours (MHr) 27 comma 000 41 comma 000 Direct materials $ 57 comma 000 $ 480 comma 000 Calculate the predetermined overhead allocation rate. (Round your answer to the nearest cent.)

+5
Answers (1)
  1. 10 August, 10:07
    0
    Estimated manufacturing overhead rate = $1.53 per machine hour

    Explanation:

    Giving the following information:

    The company allocates manufacturing overhead using a single plantwide rate with machine hours as the allocation base.

    The estimated overhead costs for the year are $ 104,000.

    Machine hours (MHr) = 27,000 + 41,000 = 68,000 machine hours

    Estimated manufacturing overhead rate = total estimated overhead costs for the period / total amount of allocation base

    Estimated manufacturing overhead rate = 104,000/68,000 = $1.53 per machine hour
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Tungsten, Inc. manufactures both normal and premium tube lights. The company allocates manufacturing overhead using a single plantwide rate ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.