Acitelli Corporation, which applies manufacturing overhead on the basis of machine-hours, has provided the following data for its most recent year of operations. Estimated manufacturing overhead $357,000 Estimated machine-hours 8,500 Actual manufacturing overhead $358,000 Actual machine-hours 8,560 The estimates of the manufacturing overhead and of machine-hours were made at the beginning of the year for the purpose of computing the company's predetermined overhead rate for the year. The predetermined overhead rate is :

+2
Answers (1)
  1. 1 April, 23:12
    0
    The predetermined overhead rate is 42 $/h.

    Explanation:

    The predetermined overhead rate is calculated by the estimated manufacturing overhead divided by the estimated machine hours.

    Predetermined overhead rate = $357000/8500h = 42 $/h
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Acitelli Corporation, which applies manufacturing overhead on the basis of machine-hours, has provided the following data for its most ...” in 📗 Engineering if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers