Ask Question
31 July, 16:31

In assigning a value for the most pessimistic (b) duration, the project manager should estimate the duration of the activity to have a 99% likelihood that it will take b or less amount of time.

a) true

b) false

+4
Answers (1)
  1. 31 July, 16:45
    0
    The correct answer is True.

    Explanation:

    This type of practice is common to evaluate the conditions in the most pessimistic scenario. The 99% accuracy is fundamental to set the most pessimistic duration of a project, because it guarantees to have a high confidence interval to ensure that the actual duration will be equal or less than the most pessimistic duration.

    Have a nice day!
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “In assigning a value for the most pessimistic (b) duration, the project manager should estimate the duration of the activity to have a 99% ...” in 📗 Physics if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers