Tony has realized that two activities (A and B) in his project cannot be done at the same time because not enough resources are a days. Activity B has 2 slack vailable. Activity A is critical and has a duration of 5 should be scheduls days of slack and a duration of 2 days. How will he decide which activity

A. He should schedule activity A first

B. He should schedule activity B first

C. He should schedule both activities A and B at the same time

D. He should schedule the activity with the least cost

E. None of the above is feasible

+2
Answers (1)
  1. 10 December, 11:27
    0
    He should schedule the activity with the least slack, that means the activity B.

    So, B. He should scheduel activity B first.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Tony has realized that two activities (A and B) in his project cannot be done at the same time because not enough resources are a days. ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.